DynaMight
Member
Which year? 2011?
Thanks for the update Ed -
But what is the chance of us getting a "definitive" yes or no statement
...
It is however true that orders will be satisfied in order, rather than strictly based on which batch you ordered from. However, since it seems that 4000 won't leave final assembly until after christmas the distinction is maybe moot. People who ordered in July 2010 will probably know over the holiday if they should be expecting a parcel in the first week of January. People ordering now - who knows.ED said clearly that there will be 3 shipments of 1000 boards between November and December, completing the first 4000 units of batch one. You won't be seeing batch 2 until after Christmas.
There is no socketed nubs? Only soldered? :huh:It takes a little more than a week to solder 2000 nubs on 1000 boards (and test them), the first shipment of 1000 boards therefore is scheduled for November 24th.
We don't even have non-socketed nubs yet! Socketed nubs are for the future as it would entail a re-design of the nub.There is no socketed nubs? Only soldered? :huh:
Hi Ed,
many thx for this great update.
how are the lcd cabels running? because i thought u had a prob with them aswell...
We didn't sell 4000 units (as that would be totally crazy, you always have to keep some for RMAs)
Oh really?ED said clearly that there will be 3 shipments of 1000 boards between November and December, completing the first 4000 units of batch one. You won't be seeing batch 2 until after Christmas.
is that true? if so, why did i receive an email saying...
> Yes your order has been received. You are approximately 3900 - 4000.
Added to the wish list (right after the socketed nubs): LCD cables with ZIF connectors...Not really. Here is what we know about the LCD cables:
* A lot from the first produced units failed, since we didn't know they need to be placed 99% accurate.
* Only 3 - 4 from the later produced units failed, there seem to be some with a lower quality. Some fail directly after installing. Don't seem to be a lot, though. Thank god.
* My unit (December last year) is still working fine with the LCD cable. And I open and close it about 10 - 15 times a day.
Therefore, the current LCD cables seem fine, there are just some that are a bit dodgy from the very beginning and they might fail.
However, as that doesn't mean they will survive forever and ever, so we are trying to be extra careful.
That's why I analyzed exactly where they fail and when, made some document and a lot of pictures showing where they are being bent and we got a new Flex Cable company suggested by MSI (Fatih has friends there) that knows a lot about flex cables and clamshell designs.
We will get samples of their produced cables in approx. 14 - 20 days.
As only the cable is being produced anew, it's fully compatible with all delivered units so far. So in case any LCD cables fail in the future (doesn't seem to be a lot based on our current experiences though), they will be replaced with the higher quality ones.
I hope that's true. A Pandora would be the perfect X-mas present. Being bumped to second batch would suck donkey poo...I'm not your distributor, so I cannot tell you for sure.
But we expected about 10 units per 100 to put aside.
We need RMA units from the very beginning, so it might be that Queue numbers 0 - 100 are are only 90 shipped and 10 for RMAs.
If its so clear, then why have 2 people asked if Batch 2 and Batch 1 are combined?ED said clearly that there will be 3 shipments of 1000 boards between November and December, completing the first 4000 units of batch one. You won't be seeing batch 2 until after Christmas.
So are these cables being put on the ones that you are going to be shipping in Dec. 2010 or is it just something you will be comparing to what you have?Not really. Here is what we know about the LCD cables:
* A lot from the first produced units failed, since we didn't know they need to be placed 99% accurate.
* Only 3 - 4 from the later produced units failed, there seem to be some with a lower quality. Some fail directly after installing. Don't seem to be a lot, though. Thank god.
* My unit (December last year) is still working fine with the LCD cable. And I open and close it about 10 - 15 times a day.
Therefore, the current LCD cables seem fine, there are just some that are a bit dodgy from the very beginning and they might fail.
However, as that doesn't mean they will survive forever and ever, so we are trying to be extra careful.
That's why I analyzed exactly where they fail and when, made some document and a lot of pictures showing where they are being bent and we got a new Flex Cable company suggested by MSI (Fatih has friends there) that knows a lot about flex cables and clamshell designs.
We will get samples of their produced cables in approx. 14 - 20 days.
As only the cable is being produced anew, it's fully compatible with all delivered units so far. So in case any LCD cables fail in the future (doesn't seem to be a lot based on our current experiences though), they will be replaced with the higher quality ones.