My normal daytime job is still giving me a lot of work... I had to edit 3 commercials and one cooking show last week, so combined with the daily shippings in my shop, I didn't have much time for anything else.
Of course, that doesn't mean nothing has happened, as there are other people working on the Pyra
1. The mainboards
The bare prototype mainboards (which most likely won't be different from the production run mainboards) will arrive at Global Components December 12th and will be populated shortly after (like the CPU boards, 30 in number).
As soon as we have the cases and the keymats for those, we can assemble them for devs, Pyra preorderers and the remaining ones will be auctioned so anyone can get them (yes, the vouchers for the Pyra can be used to get one of those if you like).
These will clearly be marked being prototypes, so they might be of some value to you
Speaking of keymats and cases...
2. The keymats
I received some inbetween sample of the keymat, but it was a bit rushed (as they wanted to finish it as fast as possible) and in my opinion, it was way too stiff.
I told them to hurry but not rush. It's more important to get perfectly working samples one or two weeks later instead of imperfect ones as fast as possible.
The good thing is, once they're working perfectly, mass production of them won't take long and can be done within a few weeks.
I'll keep you posted. This won't prevent me from building a new prototype though, as the look of the keymat won't change, only the stiffness and feel of it.
3. The cases
According to UPS tracking, a sample of the new case including the sealing for the speakers has been shipped November 28th and will arrive tomorrow until the evening.
Let's hope everything will be fine now - but we won't find that out until tomorrow or Tuesday (depending whether UPS will keep their time )
Of course you can expect some highres pictures of those - but don't expect them to LOOK perfect, as the moulds won't be hardened before everything is 100% okay physically (and therefore you will probably see a few discolorations in there).
Once the new mainboards are finished, I can finally built a prototype that works perfectly fine using a battery, as these will have the battery connectors in the proper position (running it with battery was a bit of hit and miss before).
UPDATE (did I mention I had too much work? I almost forgot this
4. The CPU boards
Nikolaus has been done countless tests (also huge thanks to notaz for a NEON-Stresstest-tool) to rule out different possibilities why the CPU boards could fail running higher than 1,2GHz. It could've been the RAM, the clock itself, power source, software settings, etc.
With these tests we could slowly rule out various issues. The RAM is fine, the power source is fine, so what we're most likely missing are some more decoupling capacitors.
So there's a very good change the next CPU boards will work fine. I'll let you know once I get more details.
Exciting times
Of course, that doesn't mean nothing has happened, as there are other people working on the Pyra
1. The mainboards
The bare prototype mainboards (which most likely won't be different from the production run mainboards) will arrive at Global Components December 12th and will be populated shortly after (like the CPU boards, 30 in number).
As soon as we have the cases and the keymats for those, we can assemble them for devs, Pyra preorderers and the remaining ones will be auctioned so anyone can get them (yes, the vouchers for the Pyra can be used to get one of those if you like).
These will clearly be marked being prototypes, so they might be of some value to you
Speaking of keymats and cases...
2. The keymats
I received some inbetween sample of the keymat, but it was a bit rushed (as they wanted to finish it as fast as possible) and in my opinion, it was way too stiff.
I told them to hurry but not rush. It's more important to get perfectly working samples one or two weeks later instead of imperfect ones as fast as possible.
The good thing is, once they're working perfectly, mass production of them won't take long and can be done within a few weeks.
I'll keep you posted. This won't prevent me from building a new prototype though, as the look of the keymat won't change, only the stiffness and feel of it.
3. The cases
According to UPS tracking, a sample of the new case including the sealing for the speakers has been shipped November 28th and will arrive tomorrow until the evening.
Let's hope everything will be fine now - but we won't find that out until tomorrow or Tuesday (depending whether UPS will keep their time )
Of course you can expect some highres pictures of those - but don't expect them to LOOK perfect, as the moulds won't be hardened before everything is 100% okay physically (and therefore you will probably see a few discolorations in there).
Once the new mainboards are finished, I can finally built a prototype that works perfectly fine using a battery, as these will have the battery connectors in the proper position (running it with battery was a bit of hit and miss before).
UPDATE (did I mention I had too much work? I almost forgot this
4. The CPU boards
Nikolaus has been done countless tests (also huge thanks to notaz for a NEON-Stresstest-tool) to rule out different possibilities why the CPU boards could fail running higher than 1,2GHz. It could've been the RAM, the clock itself, power source, software settings, etc.
With these tests we could slowly rule out various issues. The RAM is fine, the power source is fine, so what we're most likely missing are some more decoupling capacitors.
So there's a very good change the next CPU boards will work fine. I'll let you know once I get more details.
Exciting times
Last edited: