A look at the roadmap with some extra stuff in red
* Case Design: January 15th (check)
* Case Prototyping: approx. 1-2 weeks later (check)
* Deadline for Re-orders - Feb 6th (OP has to be notified they have been sent payment by this date to be flexible?)
* CNC Prototype ordered Feb 2nd.
* CNC Prototype Arrival Feb 9th -16th
* CNC Prototype Test conclusion Feb 26th - March 2nd
* FCC/CE Testing - Won't delay first batch
* Final production and delivery: approx. 2 - 4 weeks later (If CNC is cleared for launch)
I'd say the unofficial blog is probably pretty close.
* Case Design: January 15th (check)
* Case Prototyping: approx. 1-2 weeks later (check)
* Deadline for Re-orders - Feb 6th (OP has to be notified they have been sent payment by this date to be flexible?)
* CNC Prototype ordered Feb 2nd.
* CNC Prototype Arrival Feb 9th -16th
* CNC Prototype Test conclusion Feb 26th - March 2nd
* FCC/CE Testing - Won't delay first batch
* Final production and delivery: approx. 2 - 4 weeks later (If CNC is cleared for launch)
I'd say the unofficial blog is probably pretty close.