Hi Guys!
On openpandora.org is a small to do list. Unfortunatly, I didn't see, if the list is actual.
The List:
QUOTE
* Get the final Prototype case (finished and will ship Friday, 6th of March)
* Create the keymat mould (takes 20 - 25 days)
* Design the final keyboard layout (needs to be finished when the mould is ready)
* Create mould of final case (can be done once the case fits, takes 30 - 35 days)
* CE / FCC testing (can be done once the prototype case is here)
* Mass Production testrun for the final boards
* Stability testing (this will be fun)
* Wait for the last remaining pieces for mass production (LATEST deadline is second week of March)
* Mass Production
* Test the boards
* SHIP THEM!
How far are we now? The only thing, that i found about the list, is the first point: The Final Prototype case.
What's about the other points (the keymat, the CE / FCC Test / the last remaining pieces) ?
On openpandora.org is a small to do list. Unfortunatly, I didn't see, if the list is actual.
The List:
QUOTE
* Get the final Prototype case (finished and will ship Friday, 6th of March)
* Create the keymat mould (takes 20 - 25 days)
* Design the final keyboard layout (needs to be finished when the mould is ready)
* Create mould of final case (can be done once the case fits, takes 30 - 35 days)
* CE / FCC testing (can be done once the prototype case is here)
* Mass Production testrun for the final boards
* Stability testing (this will be fun)
* Wait for the last remaining pieces for mass production (LATEST deadline is second week of March)
* Mass Production
* Test the boards
* SHIP THEM!
How far are we now? The only thing, that i found about the list, is the first point: The Final Prototype case.
What's about the other points (the keymat, the CE / FCC Test / the last remaining pieces) ?