And a thread to define at what place on the roadmap we currently are.
And a thread to define at what place on the roadmap we currently are.
'emil10001' said:A timeline grabbed from the unofficial blog:
# CNC prototype - Done!
# Completion of factory mould for keymat
# Finalise keyboard layout
# Completion of factory mould for case
# CE/FCC testing
# Mass production test run
# Stability testing
# Arrival of last bits and pieces for production
# Commence mass production
# Commence final testing
# Start shipping
Edit:
Timeline from official blog:
* Get the final Prototype case (finished and will ship Friday, 6th of March)
* Create the keymat mould (takes 20 - 25 days)
* Design the final keyboard layout (needs to be finished when the mould is ready)
* Create mould of final case (can be done once the case fits, takes 30 - 35 days)
* CE / FCC testing (can be done once the prototype case is here)
* Mass Production testrun for the final boards
* Stability testing (this will be fun)
* Wait for the last remaining pieces for mass production (LATEST deadline is second week of March)
* Mass Production
* Test the boards
* SHIP THEM!