So based on the pandora.org page can we now work out an ESTIMATED ship date Ive had a go see below.
To-Do:
* Get the final Prototype case - DONE
* Build a test device and check if everything is okay
* Create the keymat mould (takes 20 - 25 days)
* Design the final keyboard layout (needs to be finished when the mould is ready) - DONE
* Create mould of final case (can be done once the case fits, takes 30 - 35 days)
* CE / FCC testing (can be done once the prototype case is here)
* Mass Production testrun for the final boards
* Stability testing (this will be fun)
* Wait for the last remaining pieces for mass production (LATEST deadline is second week of March)
* Mass Production
* Test the boards
* SHIP THEM!
So taking into account that some can be done at the same time as others I reckon we are looking at
Start Today - Build a test device an test it Im going to imagine allow a week for that - 4th May
-----------------------------1st bunch stuff complete 4th May----------------------------------------------------------------
Start 4th May - Keymat mould can then be created 25 days - 8th June
Create mold of final case 35 days - 22nd June
CE/FCC testing
------------------------------2nd bunch stuff complete 22nd June------------------------------------------------------------------------------
Mass production test runn 10days(Guess) - 6th July
Stability testing 5 days(Guess) 29th June
-------------------------------3rd bunch stuff complete 6th july-------------------------------------------------
Mass Production (1st boards ten days after run starts GUESS) 20th July
------------------------------4th Bunch of stuff complete 20th July---------------------------------------------
Test boards 10 Days (Guess) 3rd August
-------------------------------5th Bunch of stuff complete 3rd August-----------------------------------------
Ship them 5 days(Location dependant) - 10th August
-------------------------------First units in hand 17th August------------------------------------------------
Does that sound about right?
To-Do:
* Get the final Prototype case - DONE
* Build a test device and check if everything is okay
* Create the keymat mould (takes 20 - 25 days)
* Design the final keyboard layout (needs to be finished when the mould is ready) - DONE
* Create mould of final case (can be done once the case fits, takes 30 - 35 days)
* CE / FCC testing (can be done once the prototype case is here)
* Mass Production testrun for the final boards
* Stability testing (this will be fun)
* Wait for the last remaining pieces for mass production (LATEST deadline is second week of March)
* Mass Production
* Test the boards
* SHIP THEM!
So taking into account that some can be done at the same time as others I reckon we are looking at
Start Today - Build a test device an test it Im going to imagine allow a week for that - 4th May
-----------------------------1st bunch stuff complete 4th May----------------------------------------------------------------
Start 4th May - Keymat mould can then be created 25 days - 8th June
Create mold of final case 35 days - 22nd June
CE/FCC testing
------------------------------2nd bunch stuff complete 22nd June------------------------------------------------------------------------------
Mass production test runn 10days(Guess) - 6th July
Stability testing 5 days(Guess) 29th June
-------------------------------3rd bunch stuff complete 6th july-------------------------------------------------
Mass Production (1st boards ten days after run starts GUESS) 20th July
------------------------------4th Bunch of stuff complete 20th July---------------------------------------------
Test boards 10 Days (Guess) 3rd August
-------------------------------5th Bunch of stuff complete 3rd August-----------------------------------------
Ship them 5 days(Location dependant) - 10th August
-------------------------------First units in hand 17th August------------------------------------------------
Does that sound about right?