kingoddball, I agree with you. Here's why:
The company in Texas can populate and test 500 boards per week. So lets extrapolate...
March 22 - March 26th, 500 boards arrive in UK.
March 29 - April 1, 500 more boards should arrive in UK (1000 boards total) <--- assembly starts around April 1st
April 5 - April 9, 500 more boards should arrive in UK (1500 boards total)
April 12 - April 16, 500 more boards should arrive in UK (2000 boards total)
April 19 - April 23, 500 more boards should arrive in UK (2500 boards total)
April 26 - April 30, 500 more boards should arrive in UK (3000 boards total)
May 3 - May 7, 500 more boards should arrive in UK (3500 boards total)
May 10 - May 14, 500 more boards should arrive in UK (4000 boards total)
Assuming nothing else goes wrong and that it takes a week to assemble 500 boards and add a week or two for delivery, the earliest I anyone can getting a pandora is mid April. If you are near the end of the queue, you could get your pandora by the end of May.
Therefore if nothing goes wrong, only 2 more months!