Azure said:
What about the TV-Out cables we're still waiting on? Would spending less time on the iControlPad and more time on the TV-Out cables help get them to customers? Or is the current status TV-Out cable production out of your hands (last I remember reading there were some negotiation issues about minimum order size?)?
As said multiple times: The TV Out Cables are ready for production, but the amount (10.000 pieces!) they want at the moment is ridiculous.
As it's done by the same company that does the casing, trying to negotiate with them to get the cables in smaller amounts will certainly be easier once we got the rest of the cases (including the ones for Batch 2) from them.
So until the second batch cases are produced (most likely finished in October), it doesn't make sense discussing with them. That's something I posted a few times already.